Now that the treads are cast, wait for it to dry. So the site is a little idle but there is still much to do. We have less than 3 months to finish everything (giving notice of 30 November) or we will do some camping! Meanwhile
sanding screeds, it should be sanding walls and ceilings (not the most interesting part), terminate the electricity pass underlayment ...
Otherwise it remains the garage that is still raw. Initially we wanted to do later, but finally, last weekend we decided to go in its development: wooden floor upstairs to serve as attic and have a storage space, ceiling insulation and lamination . It took us 3 1 / 2 days to do everything. We worked hard:)





Monday morning, the party wall with the house has been doubled.